Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
台61線台南七股交流道至十份交流道明下午6點通車 – 我是在地人

台61線台南七股交流道至十份交流道明下午6點通車

Booking.com

〔記者楊金城/台南報導〕好消息,台61線西濱快速公路台南七股交流道到十份交流道路段,完成3階段履勘合格,將在明天(11日)下午6點開放通車,台61線從雲林可直抵台南七股區十份交流道。

開放通車路段由七股交流道至十份交流道(台61線里程298K+613至305K+750),總長度為7.14公里,工程總建設經費約38.1億元,道路寬度為22.8公尺並配置雙向雙車道,橋下兩側為之前西濱計畫完成的南173甲線混合車道,標準寬度6.5公尺。

通車路段跨越七股溪進入七股潟湖的出海口段興建的台61線七股溪橋,採大跨距興建,橋上有景觀台,可讓遊客眺望潟湖,成為特色景觀橋。

公路總局西濱南區臨時工程處說,本通車路段原規劃期程訂於107年完成,經所有參與建設之團隊全力辦理完工通車,提早一年。並是國內道路工程碳足跡查證首例,同時取得ISO/TS 14067:2013及PAS 2050:2011兩項標準之證書,建置本土工程碳足跡參數資料庫,藉由工程減碳推動產業節能減碳之目標。

通車後,台61線與台南市市道173線及176線構成交通路網,可銜接台南市區及國8至中山高,並串聯台南濱海地區各觀光景點。未來將再興建曾文溪大橋,往南再連接至台江大道,完成大台南區三縱三橫主要道路網絡,帶動大台南地區的整體發展。

  • 車行台61線七股溪橋,兩側是南173甲線混合車道。(記者楊金城攝)

    車行台61線七股溪橋,兩側是南173甲線混合車道。(記者楊金城攝)

  • 台61線台南七股交流道至十份交流道將在11日下午6點開放通車。(記者楊金城攝)

    台61線台南七股交流道至十份交流道將在11日下午6點開放通車。(記者楊金城攝)

報導來源:自由時報【原文網址