Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
左營地下道提前開放快車道通車 韓國瑜親自主持剪綵儀式 – 我是在地人

左營地下道提前開放快車道通車 韓國瑜親自主持剪綵儀式

Booking.com

#左營 #高雄 #今日新聞NOWnews


配合鐵路地下化工程,高雄市政府陸續辦理陸橋拆除及地下道填平工程,左營地下道今(27)日下午提前開放快車道通車行駛,市長韓國瑜親自主持剪綵儀式並步行至翠華路,關心巡視道路鋪設品質,整體工程預計7月下旬完竣。

檢視相片

▲市長韓國瑜步行至翠華路,關心巡視道路鋪設品質,整體工程預計7月下旬完竣。(圖/記者郭凱杰攝,2019.05.27)

左營地下道工程全長約460公尺,原先深度約7公尺,近2層樓高度,於4月17日開工並提前完工,整平工作若沒有滾壓扎實日後恐有下陷疑慮,施工團隊不敢輕忽,共分七層按步驟分層施工確實填平,以往汛期時該處地下道積淹水頻傳,填補後可望除去淹水顧慮。

副市長李四川表示,有住戶建議一併拆除一旁高架橋,當時因交通維護問題未予拆除,未來會與交通部繼續評估討論拆除可能性,日後再向市民報告。至於5個月的道路橋樑施作及改善狀況,他說,配合鐵路地下化先後拆除5座陸橋並完成填平左營地下道,同時整修133條大小道路,改善面積約178萬平方公尺。

水利局指出,左營地下道填平工程原定5月31日第一階段通車,由於進度微幅超前於下午提前開放,而為避免汽機車爭道,初期僅開放中間雙向各一快車道供汽車通車,機車部分仍維持行駛翠華高架橋,兩側護欄不予撤除,將接續施作人行道、分隔島及側溝等設施,預計7月下旬竣工。