Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
改善積淹水 鼓山抽水站下月動工 – 我是在地人

改善積淹水 鼓山抽水站下月動工

Booking.com

鼓山抽水站將於下個月動工。(記者陳文嬋攝)

2018-08-30 00:32

首次上稿 00:06
更新時間 00:32

〔記者陳文嬋/高雄報導〕高雄市水利局為改善鼓山三路積淹水,斥資4億多元完成鼓山滯洪池等建設,近來再爭取1億元將興建1座大型10CMS抽水站,預計下個月動工,搭配台泥百年紅樓,打造船型意象,屹立鼓山運河旁,改善地方積淹水。

水利局斥資4.4億元,完成鼓山運河拓寬工程、台泥廠區明渠及滯洪池工程,近來爭取中央經費1億元,將於厚生、鼓山三路口,興建1座10CMS大型抽水站,每秒抽水量10噸,比溪州抽水站還大。

台泥同意提供鼓山廠部分土地,給市府設置大型抽水站,但因旁邊有1棟紅樓建築物,台泥為保留百年紅樓,有意申請歷史建築,研議規劃為文化專區,以紅樓磚造結構不佳,擔心抽水站工程施工,會造成紅樓建築受損,建議市府將抽水站移至鼓山橋下游。

不過水利局認為抽水站設於鼓山橋下游,會影響防洪效率,將使鼓山運河的河道通水面積縮小,鼓山運河的洪水位橋渠段可能壅高15至20公分,且鼓山橋橋梁底阻水,橋樑安全受到嚴重影響,尤其鄰近現有民房,影響民眾觀感與周邊景觀。

水利局指出,這波強降雨造成鼓山三路積水30公分,雖然雨停積水退去,地方爭取設置抽水站,市府規劃10CMS抽水站,每秒抽水量10噸,比溪州抽水站還大,一旦地方積淹水,可將水抽至鼓山運河,最後再流到愛河。

水利局說,抽水站基地最大開挖深度8公分,與紅樓相距約20公分,將採靜壓式鋼板樁,減輕擋土設施打設過程的震動,鄰近紅樓側全面採用無震動的預壘樁等工法,不會影響紅樓建築物。

水利局協調台泥達成共識,台泥強調願意負起社會責任,同意配合市府建設,抽水站將做成船型意象,屹立鼓山運河邊,象徵快樂出航,搭配台泥百年紅樓,將於下個月動工,工期預計約1年,力拚明年7月完工,改善當地積淹水狀況,達到防洪保護標準。

    報導來源:自由時報【原文網址