Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
成本增加 桃園鐵路地下化經費破千億 – 我是在地人

成本增加 桃園鐵路地下化經費破千億

Booking.com

#中壢 #桃園 #自由時報


2019-08-16

〔記者謝武雄/桃園報導〕交通部鐵道局完成桃園鐵路地下化綜合規劃,由於岸壁式月台改為島式月台增加施工成本等因素,總經費也由九六四億元修正為一○五六億元;市長鄭文燦昨天受訪時表示,當初市府只是做可行性研究報告,鐵道局進行綜合規劃時有權修正,調整經費是基於鐵路營運的車站設計等原因,如果核定過低可能導致未來發包不順利。

鐵道局完成綜合規劃

鄭文燦表示,當初市府進行可行性研究報告,總經費九六四億餘元,不過按規定,最後核定經費在綜合規劃階段,因為事涉鐵路營運,包括各站月台、車站、路型等設計,鐵道局保有最後審定權利,加上考慮工程物價指數提高,會在最後的綜合規劃進行調整。至於市府則是配合都市計畫修正、沿線土地徵收等作業,也希望綜合規劃早日核定。

鄭文燦也提到,中央對於桃園鐵路地下化地方分擔款還沒有核定,市府希望比照高雄模式、也就是工程經費的廿五%來核定,未來鐵路地下化也會有開發收益,希望沿線包括中路站、平鎮站都能進行都市計畫開發,挹注市府財政負擔。

通車時程是開工後7年

鄭文燦也提到,當初中央與地方都達成共識,通車時程是在開工以後七年,這是以綜合規劃核定日為準,核定後正式開工並在七年完工,有些先導工程已經做了,比如中壢的A23站,包括中壢臨時站,因此並沒有延後問題。

岸壁式月台 改為島式月台

預算增加主因,包含永豐、中原、平鎮等三座通勤車站,由原規劃的岸壁式月台改為島式月台,另中路車站調整為可待避車站,有助於台鐵靈活調度,另配合中壢站軍用月台需求,將該軍用月台移至富岡站,最後是減少用地徵收及拆遷,採軌道支承板工程工法施工所致。

報導來源:自由時報【原文網址