Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
地方接管最後一塊拼圖 大溪污水下水道2 – 我是在地人

地方接管最後一塊拼圖 大溪污水下水道2

Booking.com

大溪污水下水道2-2標動工,將是接管最後一塊拼圖。(市府提供)

[記者謝武雄/桃園報導]大溪污水下水道系統於101年完成水資源回收中心興建,日處理量3750噸,全系統污水主幹管皆已建設完成,用戶接管3844戶,達成率62%,累積已投入建設經費達11億元,市府水務局已於1月完成2-2標招標程序,工程範圍涵蓋田心里、一心里、一德里等地區,預計接管戶數為2491戶,預計後年5月完工,也完成大溪用戶接管的最後一塊拼圖。

水務局長劉振宇表示,為了完成污水下水道建設的最後一哩路,需要市民配合提供自家後巷一樓單側75公分、雙側150公分的最小施工維護空間,讓用戶接管早日進行,事實上,大溪區市民對污水下水道建設的大力支持,大部分民眾都配合工程進度自行拆除後巷障礙物,讓2-1標用戶接管達成率達99%。

劉振宇說,市府於2016年起逐年編列預算經費,同步進行後巷環境改造工程,透過居民共同參與美化設計方案的討論,做出符合民眾生活需求的工程,達到市府與市民雙贏的目的。

    報導來源:自由時報【原文網址