Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
平鎮工業區南豐路口開瓶 拓寬疏解壅塞 – 我是在地人

平鎮工業區南豐路口開瓶 拓寬疏解壅塞

Booking.com

▲平鎮區工業五路及南豐路路口十分狹窄,拓寬後將疏解當地交通。(圖/桃園市政府提供)

▲平鎮區工業五路及南豐路路口十分狹窄,拓寬後將疏解當地交通。(圖/桃園市政府提供)

記者楊熾興/桃園報導
桃園市平鎮區工業五路及南豐路路口開瓶計畫,16日舉行拓寬工程開工,雖然拓寬路段長度約100公尺,但完工後可增進南豐路東西向聯結中興路及中豐路等南北向幹道的交通效益,並疏解上下班民眾壅塞更大幅改善平鎮工業區聯外交通。

▲▼瓶頸拓寬後不僅疏解上下班民眾壅塞更大幅改善平鎮工業區聯外交通。(圖/桃園市政府提供)

▲▼瓶頸拓寬後不僅疏解上下班民眾壅塞更大幅改善平鎮工業區聯外交通。(圖/桃園市政府提供)

▲▼瓶頸拓寬後不僅疏解上下班民眾壅塞更大幅改善平鎮工業區聯外交通。(圖/桃園市政府提供)

主持開工的副市長王明德表示,平鎮區南豐路工業段道路拓寬工程起點為平鎮工業區工業五路及南豐路路口,訖點為南豐路工業段底,屬於平鎮(山子頂地區)都市計畫,改善總長度約100公尺。目前現況寬約6公尺,規劃拓寬為8公尺寬,總經費新台幣1559萬33元,其中工程費883萬6073元、用地費675萬3960元,包括拓寬、設置擋土牆、排水及照明工程等,預計今年12月完工,完工後將為地方帶來更便捷的交通環境。

王明德特別感謝台電協助遷移變電站相關設備,原需48個月的遷移時間,經市府與台電協調,台電全力配合遷移,提早於今年6月完成。另外,也感謝「穎台科技股份有限公司」、「台灣晶技股份有限公司」2家公司願配合市府協議價購土地,讓市府順利取得用地、進行拓寬工程。

報導來源:ETNEWS新聞雲【原文網址