Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
大潭電廠7號機延長運轉 環評初審卡關 – 我是在地人

大潭電廠7號機延長運轉 環評初審卡關

Booking.com

#觀音 #桃園 #自由時報


2019-07-03 13:02

〔記者劉力仁/台北報導〕擔心電力出現缺口,台電申請大潭電廠7號單循環機組運轉時間展延至2022年底,並承諾引進最新型的氮氧化物燃燒器(LNB)污染減量技術,今天環評初審會議,環評委員要求台電再詳加評估污染物減量程度、分析對於竹苗空品區影響,補件後再審。

大潭火力電廠位於桃園縣觀音鄉大潭濱海工業區,主要供應北部地區電力,廠區裝設有以天然氣發電的6部複循環機組及1部單循環機組,裝置容量合計498.42萬瓩。

2017年6月,政府因應缺電危機決定在大潭電廠增建機組,向美國奇異公司採購2部容量各300MW的單循環的汽渦輪發電機組,裝置為大潭7-1與7-2號機,2單循環機組原先訂2019年運轉,之後改興建為大潭複循環7號機,但台電申請展延至2022年底。

台電解釋,因民營電廠IPP2(50萬瓩)招標案不如預期,加上2018年起台中火力發電廠核可用煤量自2100萬噸削減至2020年的1260萬噸,興達電廠也削減秋冬生煤許可量30%至50%,為銜接電力缺口,因而提出展延。

環保署今天舉行「大潭電廠增建燃氣複循環機組環說書第三次環差暨變更審查結論」專案小組第2次初審會議。台電表示7號單循環機組將引進最新型的LNB技術,108年底改善後NOx排放濃度將可從25ppm降至8ppm,符合環評承諾,後續再裝設選擇性觸媒轉化器(SCR),進一步將NOx濃度由8ppm降至5ppm;還有原計畫環評承諾NOx排放總量可由每年2741公噸降至1713公噸,減量1028公噸,減幅達37.5%。

環評委員認為台電必須更詳實環境衝擊評估、延長營運對苗栗及新竹地區臭氧、PM2.5污染濃度增量程度及影響也要再釐清,還有變更後生水儲槽總量存也需要確認,要求台電補充資料再審查。

                        <p>大潭電廠7號機延長運轉衝擊竹苗空品區,環評委員要求台電分析對於竹苗空品區影響,補件後再審。(記者劉力仁攝)</p>

報導來源:自由時報【原文網址