Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈北部〉《桃園》捷運綠線共線道路用地 明年2月取得 – 我是在地人

〈北部〉《桃園》捷運綠線共線道路用地 明年2月取得

Booking.com

#八德 #桃園 #自由時報


2019-05-29

〔記者謝武雄/桃園報導〕配合桃園綠線捷運施工,市府將開闢「介壽路至建德路」共線道路,起點為八德區建德路興仁夜市旁的G01站,終點為介壽路、巧克力街口的G03站,途經G02站,規劃全長一.七公里,路寬四十米,為雙向六線車道,新建道路總經費約十二.五億元,其中用地費八.二億元,預計明年二月完成捷運共線段用地取得,並配合綠捷工程期程推動闢建。

八德介壽至建德路 花12.5億闢新路

市府秘書長代工務局長黃治峯表示,「八德區介壽路至建德路新闢道路」原名為六號生活圈道路,從八德擴大都市計畫建德路、興豐路口沿仁德一街,穿越建國路、豐田路後沿產業道路連接介壽路、巧克力街旁,新闢道路將配合捷運綠線土木工程,委託捷運施工單位一併施作。

用地費8.2億 逾7成6為私有地

「八德區介壽路至建德路新闢道路」將徵收用地面積為八萬五千平方米,其中私有土地六萬五一七七平方米、占七十六.六八%,桃園農田水利會土地八二八四平方米、占九.七五%,餘為公有土地。

市府統計,徵收主要範圍在八德區建國段、大庄段、福興段等處,必須徵收約一○四筆地號土地、所有權人三八九人,會以協議價購方式並參考市價取得土地,必要時才會採取徵收手段,以提高速度。

為加速道路用地取得,議員呂林小鳳積極介入協調,包含協調保留邱家祠堂,通過建國工業區後方路線採截彎取直、讓廠房保持完整不必拆除,而預定路線通過一家工廠,經協商該工廠可於三年後再拆除,減少相當阻力。

沿G01到G03站高架段 全長1.7公里

綠線捷運從G01站到G03站採高架建構,進入G03站後才改行地下,G03站將為地下車站,而綠捷也從G03站後沿著介壽路下方直到G07桃園火車站,從G03站到G07站為GC02標的地下潛盾工程。

報導來源:自由時報【原文網址