Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
基隆輕軌延伸南港 3方案評估年底拍板 – 我是在地人

基隆輕軌延伸南港 3方案評估年底拍板

Booking.com

基隆輕軌將延伸至南港站,交通部次長王國材今天提出3方案,包括維持原本路線、延伸南港站並採地下化,或市民大道平面路段延伸南港站,預計年底定案。

交通部日前和台北市政府取得共識,基隆輕軌將以延伸至南港站為目標,王國材今天召開記者會,說明將評估3方案,包括維持原本路線、延伸南港站並採地下化,或市民大道平面路段延伸南港站,年底就會決定要怎麼做。

王國材表示,基隆輕軌原案從基隆車站到南港展覽館站,預估花費新台幣81.34億元,延伸南港站要再增加50億元經費,可行性研究將針對3個方案討論,也會評估成本效益。

至於期程方面,根據交通部規劃,基隆輕軌將在108年2月完成綜合規劃與設計、將於108年6月動工、110年10月完工與各項測試,並以111年5月正式通車為目標。

報導來源:聯合新聞網【原文網址