Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
輕軌延伸到南港站 蔡適應:基隆不用出錢 – 我是在地人

輕軌延伸到南港站 蔡適應:基隆不用出錢

Booking.com

基隆輕軌紛紛擾擾,基隆市長林右昌日前砲轟台北市長柯文哲沒有格局,感覺基隆市像是被綁架。立委蔡適應昨天表示,基隆輕軌從南港展覽館延伸到南港站需多出50億元經費,北市長柯文哲初步說願意分擔,基隆市政府不用出錢。

對於立委蔡適應的說法,台北市政府發言人劉奕霆表示,北市府將等到交通部對基隆輕軌的可行性評估出來,台北市該負擔的,台北市都會出,北市長柯文哲關心的是沒有整體規畫,若缺乏規畫造成後續追加預算,原先的財務規畫就變成虛假。

立委蔡適應說,基隆輕軌南港展覽館延伸到南港車站,基隆火車站延伸到西三四碼頭會展中...
立委蔡適應說,基隆輕軌南港展覽館延伸到南港車站,基隆火車站延伸到西三四碼頭會展中心,兩市長要求分段處理,預算一次編足,他支持這方案。 記者吳淑君/攝影
分享

立委蔡適應說,基隆輕軌原始規畫是從南港展覽館到基隆火車站,經費81億元、4年完成,現在台北端若要從南港展覽館延伸到南港火車站,基隆端從基隆火車站延伸到西三四碼頭會展中心,2市有共識要求分段處理,預算一次編足,他也支持。

立委蔡適應指出,基隆輕軌南港展覽館到基隆火車站的軌道是現成的,南港展覽館到南港站間軌道,現行方案走南港路需封路施工,工期可能會超過4年,基隆車站延伸路段搭配西三四會展中心BOT興建案,港公司預計今年招標,明年BOT廠商徵選,就可以確認工期。

「不管延伸2站工期多久,南港展覽館到基隆火車站至少4年內要通車,」蔡適應表示,基隆輕軌經費全由前瞻計畫負擔,延伸到南港站多出的50億元經費,誰出錢還沒討論到,但因全在台北市路權範圍內,台北市長柯文哲初步說願意分擔,也有可能是中央全額負責。

報導來源:聯合新聞網【原文網址