Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
速補件速排審 環評才能嚴謹又明快 – 我是在地人

速補件速排審 環評才能嚴謹又明快

Booking.com

記者劉力仁/特稿

環評到底要多快才算快?是企業界跟環保界爭論無解的話題。企業界著眼的是競爭力,環保界擔心環境被破壞,雙方如同生活在平行時空,難以交集。但可以確定的是,環評制度有其標準流程,不遵行的後果,往往是越想快則越慢。

連接雙北的淡北道路規劃案,因經過淡水紅樹林保護區,引發自然生態與道路開發爭議,九十八年新北市府送環說書至環保署審查,一百年六月有條件通過環評,但居民及環團認為環評審查並未詳評該工程對於紅樹林生態的影響,採取行政救濟,一○三年十二月最高行政法院以「審查結論出於錯誤事實認定或不完全資訊」撤銷環評審查結論,工程迄今停工,重新進行環評。

美麗灣渡假村、中科三期「停工不停產」等許多環評撤銷案,也都有類似狀況。

回到觀塘工業區第三接收站環差案,工業局今年四月送件,六月五日環評專案小組舉行第一次會議,環評委員根據環差報告書中,工業局自行提及施工時恐造成藻礁生態系不良影響,進一步提出四點質疑,包括藻礁生態現地調查、藻礁保護區影響評估、藻礁保育因應對策、藻礁保護區補償規劃,要求開發單位補件再審。

就環境專業而言,環評委員的質疑不無道理。再就歷年重大環評案結果來看,環評委員若不提出專業意見並嚴謹審查,最後極可能成為居民、環保團體提告的依據。一旦進入訴訟程序,不僅曠日廢時,如果敗訴,極可能回到原點,開發單位必須重做環評。

林全院長上任後,強調將建構「明確、有效率」之環評制度,環保署擬修改子法,希望開發單位送審之後六個月到一年,可完成環評審查,依此類推,環差審查時間可更縮短 。因此,對工業局及中油而言,盡速補件,環保署盡速排審,是最佳方案。換句話說,最嚴謹的環評,才是最快速的環評。

  • 提供大潭天然氣電廠的觀塘工業港第三接收站,目前因環差卡關。(台電提供)

    提供大潭天然氣電廠的觀塘工業港第三接收站,目前因環差卡關。(台電提供)

報導來源:自由時報【原文網址