Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
環狀線第一階段年底完工!中和站開發大樓 – 我是在地人

環狀線第一階段年底完工!中和站開發大樓

Booking.com

#坪林 #新北 #自由時報


2019-07-03 12:57

〔記者邱書昱/新北報導〕新北市長侯友宜今天視察環狀線的捷運中和站,預計今年底完工,新北捷運局表示,中和站規劃地上14層、地下4層使用,樓上層將提供商務辦公空間,並且與旁邊的南山威力廣場增設連通道,目前已有2總廠商投標,能夠挹注7億元的開發效益到新北軌道建設基金。

環狀線是從大坪林站到新北產業園區站,全長15.4公里、共14個車站,而10個車站規劃做為土地開發,預計挹注80億元捷運自償性經費。新北捷運工程局長李政安表示,目前環狀線機電系統已經完工,正進行交通部的初履勘前穩定性測試。

侯友宜與在地議員、里長前往捷運中和站會勘,並試捷運車廂,他表示,由於中和交通壅塞,因此捷運採高架建設,中和站也是連接捷運萬大線的交接點,目前正在試運轉階段,經過將近45度的轉彎幅度,發出的噪音引起周遭民眾抗議。

對此,李政安說,會先完成列車車輪切削、全線軌道磨軌作業外,也會對隔音牆改善,並延伸骨架加裝吸音板,針對路段特性擬定具體方案,對於轉彎半徑因車輛與軌道摩擦產生尖銳聲音,將安裝鋼軌潤滑器來降低噪音,目標8月底完成。

另一方面,捷運局表示,中和站土地開發案已公開徵求投資人並於5月截止,目前有2組廠商投標,今年完成資格審查及規格評選,地上4到14樓為商辦大樓,地下1樓到4樓則是停車空間,預估開發後總銷售效益約28.3億元、可挹注捷運自償性經費約7億元。

相關影音

                        <p>侯友宜(中)與在地議員、里長一起試乘捷運車廂。(記者邱書昱攝)</p>                                <p>捷運中和站採高架模式,減少中和交通壅塞問題。(記者邱書昱攝)</p>                                <p>捷運環狀線第一階段預計今年底完工,從大坪林站到新北產業園區站,全長15.4公里、共14個車站。(記者邱書昱攝)</p>

報導來源:自由時報【原文網址