Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈北部〉疏濬挨批牛步 苗栗縣府趕9月底完工 – 我是在地人

〈北部〉疏濬挨批牛步 苗栗縣府趕9月底完工

Booking.com

2018-08-25 原由地方負責 今年由縣府統籌

〔記者蔡政珉/苗栗報導〕苗栗縣政府為改善過去各鄉鎮市疏濬工程步調不一,今年改由苗縣府統籌,但因承辦業務量與首度統籌等因素,一度遭批評速度牛步。苗栗縣政府原本預計十月底完成疏濬工程,現在加緊腳步盼在九月底完成。

水利處:分3區清淤 全長140公里

苗栗縣政府水利處表示,縣管河川及區域排水疏濬清淤暨河道整理工程分為北區、中區、南區,總經費約四千六百餘萬。統計縣內排水路需要清淤長度約一百四十公里長,且清淤作業仍要將雜草木等運除,更要編列相關護岸堤防基礎補強加固項目等。

苗縣水利處將縣內清淤區域分為三區,統計至八月中旬,目前北、中、南區累積進度分別為六十一.三%、六十五%、五十二%。

苗縣府水利處說,北區包括竹南、頭份、造橋、苗栗、南庄、公館等鄉鎮市,需疏濬總長度約四十九公里,累積完成三十一公里。

中區則為後龍、通霄、西湖等鄉鎮,疏濬總長八十公里,已完成五十二公里。至於南區則有銅鑼、大湖、苑裡、三義、卓蘭各鄉鎮,疏濬總長約五十二公里,已完成廿七公里。

縣民指出,近來大雨連連,中南部縣市甚至上演馬路變小河狀況,可見河川清淤疏濬保持排水暢通重要性。希望苗縣府能記取今年作業太慢教訓,盡快完成疏濬作業,以防汛期遇到大雨造成災情。

  • 苗縣疏濬工程收回縣府辦被嫌慢,趕工拚9月底完成。(記者蔡政珉攝)

    苗縣疏濬工程收回縣府辦被嫌慢,趕工拚9月底完成。(記者蔡政珉攝)