Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈北部〉龍鳳漁港聯外道 拓寬案終過關 – 我是在地人

〈北部〉龍鳳漁港聯外道 拓寬案終過關

Booking.com

#竹南 #苗栗 #自由時報


2019-06-11

〔記者鄭名翔/苗栗報導〕苗栗縣政府獲交通部補助,擬拓寬竹南鎮龍江街,改善龍鳳漁港聯外交通問題,卻因工程經過福爾摩沙高速公路橋墩,受限交通部高速公路局的耐震補強法規而卡關,立法委員陳超明昨召開協調會,苗栗縣政府工務處提出拆除邊坡堤防,緊貼橋墩施作基樁,而高公局則於另一側擴柱補強,方案終取得各方共識,預計最快十月動工。

變更設計 避開福高橋墩

龍鳳漁港主要聯外道路龍江街僅十米寬,苗縣府前年獲補助三點七億元,去年啟動龍鳳大排加蓋、拓寬工程,但工程設計階段時卻發現,加蓋基樁其中一段從福高高架橋下穿過,與國道橋墩位置重疊,按高公局規定,基於二○二一年將進行耐震補強工程,橋墩周遭三公尺內不得施工,導致道路拓寬工程卡關。

苗縣府委外設計單位原提出方案,希望於橋墩三公尺範圍外以ㄇ字型架樑方式,從橋墩上方避開,但高公局指出,未來橋墩耐震補強將於結構上方增厚半公尺,因此基座上方不得有其他構造物。

協調3次 高公局點頭

苗縣府工務處昨再提出新方案,擬將破壞現有龍鳳大排十八公尺長堤防,將基樁緊貼橋墩,完成後再修復堤防,此案已經過水利處原則允准;高公局經評估後,也認定此方案可行,後續福高橋墩擴柱方式將避開基樁,而向另外一側加倍增寬。歷經三次協調後,雙方終於取得共識。

立委陳超明表示,樂見此工程終取得共識,但後續拆除堤防的費用還須經設計單位於一週內送交規劃書,未來希望高公局能支援財政窘困的苗縣府這筆費用。而龍鳳漁港聯外道路拓寬計畫預計最快可於今年十月動工,盡快改善交通問題,帶動當地觀光休閒漁業發展。

報導來源:自由時報【原文網址