Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈北部〉苗栗北橫最後一哩 中央審議通過 – 我是在地人

〈北部〉苗栗北橫最後一哩 中央審議通過

Booking.com

〔記者彭健禮/苗栗報導〕苗栗縣「北橫公路」,歷經近廿年持續推動,「最後一哩路」斗煥坪至三灣段的工程用地徵收計劃於九日獲內政部審議通過,苗縣府預計於九月辦理工程招標作業,拚年底發包施工,期許早日通車,改善區域交通瓶頸,也串連山、海線觀光旅遊資源。

苗栗北橫公路全長十一.六五公里,由苗縣府於八十七年起規劃啟動興建,從台一己線連接福爾摩沙高速公路,並與中山高速公路、台一線及台三線交會,為串通竹南、頭份到三灣、南庄的橫向交通,因土地取得及工程經費龐大等因素,分為四期推動。

四期工程分「永貞路至頭份大橋段」、「頭份大橋至雞心壩段」、「雞心壩至斗煥坪段」、「斗煥坪至三灣段」。雞心壩至斗煥坪段已於九十九年完工;永貞路至頭份大橋段於今年一月通車;頭份大橋至雞心壩路段,預計今年十二月完工;剩斗煥坪至三灣段尚未施做。

縣府工務處表示,斗煥坪至三灣段工程,全長約三公里,於一○五年五月核定納入交通部公路總局「生活圈道路交通系統建設計畫」補助辦理,工程總經費十七億九千多萬元,中央補助十五億五千多萬元經費,縣府配合二億三千多萬元;工程用地徵收計畫,也於九日獲內政部審議通過。

工務處指出,現正辦理用地取得作業,拚年底發包施工;工程將從斗煥坪已完成的前期工程,採高架橋樑跨越中港溪,平安大橋至水頭屋大橋部份則沿中港溪左岸採路堤方式施作,直至水頭屋大橋轉向東銜接台三線峨眉橋,預計一○九年年底完工。

工務處表示,全線通車後,不僅可紓解苗一二四號縣道尖峰時段及假日車流量,也串連竹南、頭份、三灣及南庄等鄉鎮的觀光及產業經濟發展。

  • 苗栗縣「北橫公路」斗煥坪至三灣段,全長約三公里,工程用地徵收計劃於九日獲內政部審議通過,苗栗縣政府預計於九月辦理工程招標作業,拚年底發包施工,改善區域交通瓶頸,也串連山、海線觀光旅遊資源。(記者彭健禮翻攝)

    苗栗縣「北橫公路」斗煥坪至三灣段,全長約三公里,工程用地徵收計劃於九日獲內政部審議通過,苗栗縣政府預計於九月辦理工程招標作業,拚年底發包施工,改善區域交通瓶頸,也串連山、海線觀光旅遊資源。(記者彭健禮翻攝)

報導來源:自由時報【原文網址