Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
苗栗兩廢校陸橋拆除 台13甲改善工程拚9月底完工 – 我是在地人

苗栗兩廢校陸橋拆除 台13甲改善工程拚9月底完工

Booking.com

#造橋 #苗栗 #自由時報


2019-07-08 12:47

〔記者鄭名翔/苗栗報導〕台13甲線苗栗縣造橋隧道至北勢大橋截彎取直、拓寬工程正進入最後一哩路,公路總局連3天拆除已廢校的豐湖、富田國小前人行陸橋,屆時將規劃改道及部分路段間歇性管制通行;後續還須進行高鐵橋下道路降挖工程、彼岸橋穿管、鋪路等,預計總工程最快將於9月底完工,還給用路人安全通行環境。

台13甲線為苗栗重要南北幹道,過往因造橋段多彎道易造成車禍事故,自2012年起苗栗縣政府、公路總局進行道路截彎取直、拓寬工程,從造橋隧道至北勢大橋共六公里長,分北、中、南3段施工,目前剩南段的大衛營至北勢大橋路段尚未完工。

公路總局苗栗段長陳禎康表示,由於該路段附近多民宅,加上配合電桿移除、電纜地下化、管線遷移等作業,增加施工難度,近期又逢連日大雨,導致作業無法進行,以致工程略為順延,預計最快9月底可讓全線暢通。

而2014年陸續廢校的豐湖、富田國小前人行通學陸橋早已廢棄無人使用,為配合道路拓寬,公路總局於6日晚間10點起至7日早上5點、7日晚間10點至8日早上5點進行拆除作業,豐湖國小前路段將採階段式管制通行,富田國小前路段則依現場指揮改道新港三路、高鐵五路、新東路車道。

陳禎康說,後續還尚須進行高鐵橋下400公尺長路段降挖1.2公尺工程、並配合管線遷移,而彼岸橋主體工程已完成,但尚等管線穿線及鋪設AC路面、移除電桿等,將加速趕工,盡快提供安全、舒適的用路品質。

                        <p>造橋鄉豐湖國小已廢校,陸橋無人使用,公路總局進行拆除。(記者鄭名翔攝)</p>                                <p>台13甲線苗栗縣大衛營至北勢大橋路段改善工程預計於九月底完工。(記者鄭名翔攝)</p>                                <p>已廢校的富田國小前陸橋也將拆除。(記者鄭名翔攝)</p>

報導來源:自由時報【原文網址