Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈中部〉配合水美路路平裝自來水 每戶省2萬路修費 – 我是在地人

〈中部〉配合水美路路平裝自來水 每戶省2萬路修費

Booking.com

〔記者張軒哲/台中報導〕外埔區水美路路況不佳、人手孔蓋遍布,影響水美里居民通行,暑假將進行路平一次性翻修改善工程,全線兩千八百公尺將減少四十一個人孔蓋。自來水公司大甲營運所工務股長林哲光表示,本次配合路平專案之便,工程進行之前登記申裝自來水,每戶約可免除兩萬元路修費,水美里尚未安裝自來水家戶,可把握免繳約兩萬元路修費的良機,踴躍申裝。

水美路沿線約有四百戶住戶,除了是當地住戶道路,也是水美工業區和三清總道院進出國道三號必經之路。市議員吳敏濟表示,每天至少有數百輛大型貨車和遊覽車重壓,加上山坡地起伏,路面凹凸不平,人手孔非常多,里辦公處東邊一個下坡轉彎處,不到廿公尺就有四個大型人孔蓋,尤其對機車騎士構成極大威脅。感謝市府編列預算及中央補助,進行本次工程。

數十戶無自來水 里長將逐一通知

水美里長陳俊樑表示,里民反映水美路路況太差,又多年沒有一次性翻修,目前里內尚無自來水的用戶集中於二崁路一帶,僅剩約數十戶,會逐一通知。由於路平後,依法兩年內不得開挖,兩年後才能申裝,費用也須加計路修費,很不划算。

市府養工處第三工程隊隊長張少璞指出,本次水美路改善工程起自甲后路,結束於慶鎂紙器廠,全長兩千八百公尺。現有各單位的人手孔一一六個,屬於中華電信的人孔蓋將有四十一座下地移除,屬於消防栓和自來水公司的制水閥有存在必要,無法下地,會在施工中調整高度與路面平齊。

張少璞表示,本工程原定五月間進行,但為配合中華電信大規模光纖網路更新提速計畫,養工處要求水美路優先施工,路面改善工程順延至七至八月間進行。改善AC路面刨鋪、止滑標線、路基改良、人手孔調整等。

  • 水美路人手孔蓋過多,影響騎士安全,市府養工處將在暑假期間進行路平工程。(記者張軒哲攝)

    水美路人手孔蓋過多,影響騎士安全,市府養工處將在暑假期間進行路平工程。(記者張軒哲攝)

報導來源:自由時報【原文網址