Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈中部〉前瞻示範道 中市北屯太原路改善10月發包 – 我是在地人

〈中部〉前瞻示範道 中市北屯太原路改善10月發包

Booking.com

2018-09-14

〔記者張菁雅/台中報導〕台中市獲內政部營建署前瞻計畫補助,推動北屯區太原路三段自旱溪東路至建和路道路及人行道改善工程,做為中部地區前瞻計畫示範道路。建設局表示,預計十月底前發包,十一月動工,明年七月前完工。

太原路三段路平工程獲前瞻計畫補助,總經費一億零三二五萬元,中央及市府各負擔一半,施工範圍自旱溪東路至建和路,全長約一千六百公尺、寬約四十公尺。

建設局長黃玉霖表示,工程內容包含既有路平專案、人行道拓寬二公尺、路燈號誌共桿等,並納入自行車道、交叉路口設計無障礙斜坡道,打造綠色生態路網及都市無障礙人行空間,改善市容景觀。

後續將視經費情況,將太原路三段的快車道路面改善延伸至祥順路、廍子路交叉口,並結合通勤、運動、休閒三種功能的道路環境,成為中部地區前瞻計畫示範道路。

建設局指出,太原路三段位在台七十四線快速道路下方,過了旱溪,可抵達台鐵太原車站,是北屯區交通樞紐,又可通往大坑風景區,具觀光效益。

報導來源:自由時報【原文網址