Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈中部〉埔里福興溫泉區 第一口井挖好了 – 我是在地人

〈中部〉埔里福興溫泉區 第一口井挖好了

Booking.com

2018-09-11 原擬鑿6井改4井 成本降

〔記者陳鳳麗/南投報導〕南投縣府開發埔里鎮福興農場溫泉區,第一口井已開鑿完成,縣府決定將原擬開鑿六口井計畫修改為四口井,約可省下六、七千萬元經費,降低開發成本,屆時可優先選購的仁愛鄉廬山溫泉區業者,購地成本將因而降低。

以安置廬山溫泉業者為主要考量,南投縣府在埔里鎮福興農場開發溫泉區,原被外界質疑「沒有溫泉的溫泉區」,但縣府去年十一月鑽探八百多公尺,已挖到攝氏四十七度溫泉水,終於讓縣府放心開發。

預估投資逾三十三億元的福興農場溫泉區,基地面積達五十五.六七七公頃,除湯屋區、住宿區、遊客中心等建物外,還有溫泉廢水處理設施、停車場、親水公園和壘球場等公共設施。

堪稱全區命脈的地下溫泉,原來打算投注二億四千萬元開鑿六口溫泉井,第一口井已開鑿完成,目前正在開挖第二口井,而且因為出水量比預估高,縣長林明溱日前現勘後,指示將把六口井下修為四口。

建設處長李正偉表示,每一口井出水量每小時約三十到五十噸,一天約有八百噸,而全區一天用水量估計二千二百五十噸,四口井就足以滿足需求,因少挖兩口井,將省下六、七千萬元經費,未來廬山溫泉區業者除能以成本價優先承購土地,且能減少購地價格。

趕在明年7月完工

李正偉也說,園區各項基礎設施也正積極施作中,建築部分因取得建照及埋設管線等因素開工較晚,進度約達七成;至於第一期排水工程、污水管線及橋樑工程等進度都超過八成或完成,此外遊客中心及壘球場也開始施作,會要求包商趕工,如期在明年七月二日完成。

南投縣府開發完成福興農場溫泉區後,除優先安置廬山地區溫泉業者,剩餘的部分將公開標售,開放給有意願投資的業者進駐。

  • 南投縣長林明溱(右一)日前會勘福興農場溫泉區工程進度,指示將原定開鑿六口井改為四口。(南投縣府提供)

    南投縣長林明溱(右一)日前會勘福興農場溫泉區工程進度,指示將原定開鑿六口井改為四口。(南投縣府提供)

報導來源:自由時報【原文網址