Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
林姿妙縣長視察宜蘭橋改建工程 – 我是在地人

林姿妙縣長視察宜蘭橋改建工程

Booking.com

#員山 #宜蘭 #台灣好報


施工中的宜蘭橋改建工程。

宜蘭橋原址拆除重建,計畫內容主要將新橋配置雙向4車道,並設置人行及自行車通行空間,並提高橋面及移除舊有路堤以提高河川通洪能力。工期660日(22個月),預計於109年12月完工。

交通處指出,現階段正施作便橋工程,該部分主要在原橋的上、下游各設置便橋1座,銜接現有橋梁兩端之路口(中山路三段與環河路口、中山路五段與津梅路口),每座便橋單向通行,並配置1快車道、1慢車道及1人行道,提供原橋封閉(拆除)時,一般民眾通勤等通行使用。便橋預計於108年7月完成,同時封閉舊橋。

因現場受到現有道路空間及堤防等因素,為減少交通衝擊及安全,便橋禁止15噸以上大貨車、聯結車通行;並限制大客車通行便橋時,下橋端之路口禁止右轉。其中大貨車及聯結車部分,因主要來往員山方向,建議可改行台9線(環市東路)-環市南路-溪洲路-長堤路-台7線,或其他無禁行大型車輛之路段。另縣府亦將宣導過境性車流(汽、機車)改通行宜興橋或慶和橋等替代道路避開通行施工路段。

報導來源:台灣好報【原文網址