Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈北部〉花蓮市新興路拓寬支線工程 封路改道 – 我是在地人

〈北部〉花蓮市新興路拓寬支線工程 封路改道

Booking.com

#花蓮 #市 #自由時報


2019-05-18

〔記者游太郎/花蓮報導〕因應蘇花改全線通車後,花蓮市區將面臨車潮及交通阻塞窘境,被視為重要疏導路線的新興路拓寬工程,支線因牽涉到拆除花蓮高工宿舍及陸軍第二地區支援指揮部營舍,自即日起至明年六月一日將封路,將衝擊美崙地區前往花蓮車站的交通,花蓮市長魏嘉賢呼籲民眾配合改道。

即起至明年六月一日封路

新興路景觀改善及興闢工程去年四月動工,初步進行新興路與瑞美路口至新興路與尚志路口的主線工程,截至目前為止,施工進度為三十三.一七%,比預定進度二十四.九七%超前,但難度更高的支線工程,將封閉位花蓮高工及陸軍二支部間的道路,封閉日期從五月十五日起到明年六月一日止。

改善壅塞 支線將拓寬為25米

市長魏嘉賢指出,新興路支線是美崙地區與花蓮市區重要聯繫道路,但道路路寬僅有六公尺,常有車輛因交會發生碰撞事故及因會車等待造成道路壅塞,支線將拓寬為廿五公尺後,將可改善因道路狹窄限縮車流量形成交通壅塞情形外,也可因應未來蘇花改通車後,紓解部分通往市區的車流。

東工組主任黃銘弘表示,新興路拓寬及景觀改善工程,主要為銜接花蓮市尚志路與十六股大道兩大幹線,強化花蓮市東西向聯絡道路,及銜接台九線。原有路寬為六至八公尺道路,拓寬後為廿五公尺。

新興路工程金額為一億六千多萬元,施工區域包括主線道與支線道,主線道長度為九百九十六公尺,支線道由新興路起至中興路口止,長度為四百八十八公尺。

另外,陸軍二支部拆除的營舍位於支線拓寬道路,將由花蓮市公所執行「代拆代建」,經費六千一百萬元,去年十一月開工,將興建地上四層建築,預計今年十月完工。

花蓮市新興路景觀改善及興建工程 支線封閉路段及改道路線示意圖

報導來源:自由時報【原文網址