Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈北部〉新自強隧道雙軌化 最快6月通車 – 我是在地人

〈北部〉新自強隧道雙軌化 最快6月通車

Booking.com

〔記者花孟璟/花蓮報導〕去年九月廿六日切換通車的花東線鐵路「新自強隧道」,為雙軌化隧道,但去年起只有單線(西正線)通車,至於東正線的土建工程已在農曆年前完工,目前為電車線調整、最後測試階段。鐵工局玉里工程段表示,預計三月底報交通部進行履勘作業,預計六月份新自強隧道將可雙線通車。

鐵工局玉里工程段長薛文城說,新自強隧道去年九月第一階段通車單線,第二階段雙線通車如火如荼進行中,東正線土建工程已於一月底完工,軌道、號誌均已銜接完成,電車線已經完成架設,預計三月七日、八日兩天自主巡察,做最後調整,接下來找台鐵局聯合進行電車線、號誌線的動態測試,最後成果四月報交通部,由交通部成立履勘小組做最後確認,最快六月份新自強隧道雙線通車。

南平至萬榮9.6公里 預計109年完工

鐵工局也透露,鳳林南平至萬榮的九點六公里雙軌化工程,包括最主要的萬里溪橋改建成雙軌橋,以及鳳林鐵橋等三座小型橋樑改建。其中萬里溪橋配合水利署在萬里溪南岸退後河川治理線,堤防後退,導致原規劃橋樑長度二百四十公尺需拉長,目前還在等河川局處理堤防徵收問題才能定案,預計一○九年完工。

其餘路段預計明年設計、發包

鐵工局玉里工程段表示,目前花東線全長一百五十公里,實際完成雙軌路段僅四十五公里,不到三分之一,目前政府為加速東線鐵路雙軌化進度,除了去年十月起動工的鳳林南平至萬榮九點六公里路線雙軌化工程,預計一○九年完工,其餘路線雙軌化計畫納入行政院前瞻計畫軌道建設中,目前已進入環評階段,希望環評可於年底跑完、明年進入設計及發包階段,後年一○九年開工,才能有效提昇花東線調度彈性、減少行車時間。

  • 新自強隧道東正線土建工程已完工,正進行電車線測試作業。(鐵工局提供)

    新自強隧道東正線土建工程已完工,正進行電車線測試作業。(鐵工局提供)