Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
大潭電廠輸電線路大變更 環委要求台電補件審查 – 我是在地人

大潭電廠輸電線路大變更 環委要求台電補件審查

Booking.com

台電大潭電廠原規劃透過345kV的高壓輸電線路從桃園經新竹到龍潭,台電計畫更改路線,原向東改向北,從桃園送至新北林口電廠。(記者劉力仁攝)

首次上稿:15:11
更新時間:16:17

〔記者劉力仁/台北報導〕台電大潭電廠興建案於103年9年通過環評審查,台電計畫興建3到8部燃氣機組,裝置容量288萬瓩,透過345kV的高壓輸電線路從桃園經新竹到龍潭變電廠,台電計畫更改路線,原向東改向北,從桃園送至新北林口電廠;由於環評委員認為台電未釐清沿線文化資產保護、生態衝擊、地方溝通,要求台電補件再審查。至於今天變更路線涉及的新北市政府,環評會有邀請,但無人到場陳述意見。

環保署今天下午召開「大潭電廠增建燃氣機組發電計畫輸電線路變更」環差初審,台電原規劃大潭電廠發電後,經過桃園市觀音區、新屋區、楊梅區、龍潭區及新竹縣關西鎮等5區鎮,將電力輸送至龍潭高超壓變電所,全長33公里。沿台66、縣115、台1省道、桃67等道路下方埋設。

台電提出變更,改以161kV的高壓輸電線路,經過桃園市觀音區、大園區、蘆竹區及新北市林口區等4區,將電力輸送至林口電廠,全長30公里。沿台61道路下方埋設。

台電解釋,更改輸電路線之後,可以降低龍潭高壓電變所電力過於集中的風險,工期從93個月降至60個月,投資費用從277億元降到142億元,剩餘土石方從85萬方降至64萬方,且全線地下化,且變更後路線沿著台61線埋設,周邊主要為工業區,並未經過桃園埤圳濕地敏感區,對環境衝擊降低。

環評委員則對於施工過程中可能出現的交通衝擊、地方溝通、空氣汙染、林口電廠電力是否超載等影響,提出質疑,也有環評委員認為變更幅度太大,應該重新辦理環評案,而非用環評差異分析,比較簡略的方式送審,但委員討論之後,此次變更路線並未涉及環評法施行細則第38條之1相關規定,同意台電提送環差,但要求台電以準環評的規格進行評估。

    報導來源:自由時報【原文網址