Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈台北都會〉新北捷運環狀線一階 今全線合龍 – 我是在地人

〈台北都會〉新北捷運環狀線一階 今全線合龍

Booking.com

〔記者何玉華、翁聿煌/新北報導〕新北市「三環三線」核心第一環的捷運環狀線第一階段,今天(十二日)凌晨進行全線合龍,工程進度近八成,後續機電與軌道工程將接力進行,預計一○七年底完工。

環狀線第一階段全線十五.四公里,設十四座車站與一處機廠,行經新店、中和、板橋、新莊等人口稠密區。

市府捷運工程局局長趙紹廉指出,十二日凌晨零點,板橋區新站路上的環狀線主線最後一根軌道梁完成合龍,代表工程最難的部分已完成,環狀線工程從地面下到高架段,囊括地下車站、潛盾隧道、跨河段、平行高架段、全台首見的疊式高架段、台六十四線共構「一線天」落墩、島式月台、側式月台、中運量捷運五星級的機廠等,工程複雜及工法多樣性,可說集捷運建設技術的大全。

他舉例說,板橋文化路的板南線在地底下十二公尺,興建中的環狀線在地面上約十公尺高,兩者相差廿二公尺,但環狀線的墩柱深入地底約五十公尺,與板南線水平相距不到一公尺,鑽挖時格外小心。

另外,大坪林捷運站採潛盾工法,潛盾機鑽入營運中的新店線大坪林站正下方施工,也要避免震動與施工範圍影響營運中的路線。

中和中正路及台六十四線 施工封閉

另外,為了辦理「三環三線」捷運環狀線在中和區中正路(鄰近及橫跨台六十四線)高架橋排水工程、鋼構補漆及隔音牆組施工,即日起至十月廿五日的每天深夜十一點至翌日清晨六點,封閉中和區中正路及台六十四線。

報導來源:自由時報【原文網址