Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
中壢臨時後站 明年9月完工 – 我是在地人

中壢臨時後站 明年9月完工

Booking.com

#中壢 #桃園 #中時電子報


中國時報【呂筱蟬╱桃園報導】

桃園市長鄭文燦3日視察鐵路地下化工程,先導工程在2018年9月與機場捷運延伸線A23站工程同步啟動,截至目前為止,橫渡線降挖3.2公尺工程已完成、A23站降挖工程施工中,中壢後火車站移設工程今年4月啟動,預計2020年9月完工,目標2年內完成中壢新站地下結構體開挖。

2年內完成新站地下體開挖

鄭文燦指出,為了施做機場捷運與鐵路地下化共構範圍工程,需先將中壢後火車站遷移,臨時後站位於新興路原公車候車亭位置,等待中壢臨時車站完工後,再進行中壢站體開挖,並同步遷移鐵軌。

另外,機捷A23站先導工程目前完成中興地下道拓寬,鐵路地下化部分完成工程設計初稿,綜合規畫正報交通部審查中,若今年順利通過行政院審查,將於綜規核定後7年工期完成桃園鐵路地下化工程。目前市府與鐵道局研商,希望內壢以南的臨時軌道工程,能提早至今年6月或7月進場施工。

為了配合鐵路地下化工程,機場捷運A23站降挖5.7公尺,鐵道局於2018年9月啟動該項工程,目前正在施作東側連續壁,健行路工區採半半施工方式,保留部分車道提供車輛通行,維持健行路交通順暢。

機捷中壢段 工程進度超前

中壢後火車站的遷移工程同步規畫設置無障礙電梯,連接中壢車站前後站,以及月台的臨時後站跨站天橋,預計2020年9月完工。

鄭文燦強調,機捷進入中壢段工程目前進度超前,A22站及A23站土建工程進度超過50%,機電工程也於近日重新上網招標,希望盡快完成發包。

報導來源:中時電子報【原文網址