Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈北部〉歷經流標4次 東門市場9月動工 – 我是在地人

〈北部〉歷經流標4次 東門市場9月動工

Booking.com

〔記者陳昀/桃園報導〕市府規劃原址重建桃園區東門市場,歷經四次流標,讓地方民代擔心若無法如期興建、讓永和市場攤販遷入,將延宕桃園捷運綠線年底開工進度,還好經市府新建工程處提高招標金額,昨天終於以約六億四千七百萬元決標,九月可如期動工。

新建工程處長陳智仁表示,東門市場工程流標第三次時,新工處即檢討決定增加機電工程預算,將發包金額從六億三千六百萬元增為六億七千四百萬元,第四次招標時有二家廠商投標,因是修改金額後的第一次招標,未達三家廠商投標規定而流標,第五次招標時,這二家廠商都前來投標,最終以六億四千七百萬元決標。

陳智仁表示,新工處會盡快執行後續程序,九月即可如期動工,工期約一年十個月,最快二○一九年七月完工;市府經濟發展局表示,東門市場只要在二○一九年十月前完工、二○一九年十二月底前完成永和市場攤商遷移,就不會影響捷運綠線進度。

  • 市府規劃原址重建地下三層、地上五層,總樓地板面積五九六四坪的綜合市場大樓,圖為完工模擬圖。(市府提供)

    市府規劃原址重建地下三層、地上五層,總樓地板面積五九六四坪的綜合市場大樓,圖為完工模擬圖。(市府提供)