Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
高鐵延伸屏東站址規劃 本週審查期中報告 – 我是在地人

高鐵延伸屏東站址規劃 本週審查期中報告

Booking.com

高鐵延伸屏東站址規劃期中報告,本週召開審查會議。(記者侯承旭攝)

2018-09-10 15:39

〔記者侯承旭/屏東報導〕前瞻基礎建設「高鐵延伸屏東站址規劃作業」期中報告已經出爐,訂於9月12日審查。

前瞻基礎建設編列800萬元執行「高鐵延伸屏東站址規劃作業」,內容包括相關車站規劃及地質、管線調查等,由台灣世曦公司得標,於今年6月11日提出航空測量及地質調查初稿報告、7月13日提交期中報告。

根據交通部鐵道局官網揭露,該規劃作業訂於9月12日召開期中報告審查會議,預定於今年底前完成相關規劃。

交通部去年初投入1000萬元進行「高鐵延伸屏東新路線可行性評估」,也是由台灣世曦公司得標,規劃的新路線從高雄燕巢或高雄左營等2處分岔延伸至屏東,總經費約500億元,工期達10年,屏東端建議設站於屏東市的六塊厝地區。

    報導來源:自由時報【原文網址