Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
高壓電移室內 「板橋一次變電所」遷移2020完工 – 我是在地人

高壓電移室內 「板橋一次變電所」遷移2020完工

Booking.com

土城區「板橋一次變電所」正進行改建,未來原先暴露在外的高壓電塔(圖上方)會遷移至室內,旁邊也有0.85公頃的土地回饋給新北市政府。(台電公司提供)

2018-09-11 19:35

〔記者邱書昱/新北報導〕位在新北市土城區金城路的「板橋一次變電所」供應大台北用電,台灣電力公司進行改建工程,高壓設施將移入室內,新北市議員黃永昌昨天與台電舉辦簡報及會勘;台電透露,預計2020年底完工,未來運轉可靠度也會提升。

1969年興建的「板橋一次變電所」屬於傳統的屋外式變電所,隨著時間推移,原先周遭的農地成為工商都會區,黃永昌說,高壓電暴露在外附近居民擔心健康受影響,目前工程中也曾有住戶反映施工聲音過大的問題。

台電北區施工處課長林健民表示,興建成室內式後,有建築物阻擋,可以減少居民的擔憂,而且室外的高壓電容易受到動物、環境影響,改為室內後運轉可靠度也能提升。

針對工程噪音,台電北區施工處第五工務段第一分隊課長林宏明指出,去年接到里長反映,將工程改以切割方式將基柱夾起,不再以敲打。

林宏明說,改建完成後分為A、B兩棟合計約2.7公頃,並騰空2.1公頃的用地辦理都市計畫變更為商業用地,另外0.85公頃土地則回饋給新北市政府作為鄰里公園或兒童遊戲場。

林宏明補充說,靠近金城路段會退縮30公尺,附近種植樹木打造綠美化環境,計畫預算加上外圍配套工程約60億元,目前進度40.25%,預計2020年底完工。

  • 目前室內式變電所進度達四成,未來周遭也會種植栽綠美化。(記者邱書昱攝)

    目前室內式變電所進度達四成,未來周遭也會種植栽綠美化。(記者邱書昱攝)

  • 新北市議員黃永昌(右)向台電反映施工噪音問題。(記者邱書昱攝)

    新北市議員黃永昌(右)向台電反映施工噪音問題。(記者邱書昱攝)

報導來源:自由時報【原文網址