Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈中部〉大安南庄里、福興里自來水將延管 400戶受益 – 我是在地人

〈中部〉大安南庄里、福興里自來水將延管 400戶受益

Booking.com

預計9月動工 明年2月完工

〔記者歐素美/台中報導〕立法院副院長蔡其昌爭取中央補助六千多萬元,辦理大安區南庄里及福興里自來水延管工程,預計九月動工,明年二月完工,將嘉惠四百多戶,兩地自來水普及率也可望從廿%提高至七十四%。

蔡其昌配合「前瞻基礎建設—無自來水地區供水改善計畫」,積極向經濟部水利署及市府爭取大安區自來水延管工程;其中,南庄里獲核定補助兩千四百七十五萬元、福興里核定補助三千六百萬元。蔡其昌昨邀集經濟部水利署副署長鍾朝恭、台灣自來水公司第四區管理處處長蕭淑貞等人到場會勘,並與居民座談。

幹管至家戶 20公尺內全額補助

蔡其昌表示,偏鄉自來水問題絕對要徹底解決,這次預算的爭取,除了幹管補助外,幹管至家戶管路廿公尺內都會全額補助,再次將大安區自來水接管率往上提升。

其中,南庄里共三百五十二戶,目前自來水用戶僅四十四戶,核定受益用戶一百八十二戶,自來水普及率將從十二.五%提高至六十四%;福興里三百九十五戶,目前自來水用戶僅一百零七戶,核定受益用戶兩百廿一戶,自來水普及率也將從卅.五%提高至八十三%。

蔡其昌服務處表示,依據「自來水用戶設備外線補助辦法」,村里供水普及率低於七十%,可全額補助用戶廿公尺內的外線設備費用,超出廿公尺的費用則補助三分之二,用戶外線接水完成後,可備妥接水完成證明及預繳費用收據等,向大安區公所申請補助。

  • 立法院副院長蔡其昌(立者)邀集水利署副署長鍾朝恭及台水公司第四區管理處處長蕭淑貞等,向居民說明延管計畫。(記者歐素美攝)

    立法院副院長蔡其昌(立者)邀集水利署副署長鍾朝恭及台水公司第四區管理處處長蕭淑貞等,向居民說明延管計畫。(記者歐素美攝)

報導來源:自由時報【原文網址