Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈北部〉司馬庫斯聯外道 納入前瞻逾億元改善 – 我是在地人

〈北部〉司馬庫斯聯外道 納入前瞻逾億元改善

Booking.com

分3年施作 2020年下半年完工

〔記者廖雪茹/尖石報導〕部落人的心聲,中央聽到了!本報在二月廿八日獨家披露,新竹縣尖石鄉後山最偏遠的司馬庫斯部落,聯外道路千瘡百孔,有遊客發起一人一信請求總統幫忙改善;縣府和尖石鄉公所提案爭取前瞻基礎建設計畫,獲核定一億一千七百七十萬元總經費,部落人獲悉後無不欣喜萬分,公所預估二○二○年下半年全面完工。

尖石鄉公所建設課長劉經邦表示,司馬庫斯聯絡道路六到十六K整體道路品質改善工程提案後,特別引用本報報導,爭取內政部營建署和立委高金素梅等大力支持。因此案經費龐大,得標的顧問公司提出基本設計後,須經公所、縣府和營建署審查通過,才會辦理工程招標;如作業流程順利,預估九月前後完成發包,分三年施作。

劉經邦表示,另先前已獲原民會補助四千三百萬元,辦理司馬庫斯聯絡道路零到六K改善工程,本月底決標,預計年底完工。

施工期間規劃接駁車供族人進出

為免影響遊客上山,尖石鄉公所與司馬庫斯部落初步協調,施工期間,原則上會避開寒、暑假和連續假期,自九月開始於週一到週四將封閉道路全面施作;部落為配合工程,擬規劃接駁車供族人採買和就醫,相關交通管制訊息,屆時將公告在公所和司馬庫斯旅客服務中心官網。

考量司庫聯絡道路易崩坍等路況特性,公所研擬鋪設鋼筋水泥硬性路面,並加強排水系統、邊坡及擋土牆等附屬設施,以減少雨水沖刷、切割等影響,延長道路壽命。

司馬庫斯部落長老優勞表示,族人十分感謝政府金援和本報反映民意。他並說,聯絡道路陡坡落差大,排水系統十分重要;在地族人可依經驗提供意見,參與工程監督,以共同提升道路品質。

縣府工務處表示,山地鄉除了上案核定一.一七七億元,尖石鄉錦屏那羅溪綠水廊道(青蛙石天空步道風景區)也核定四千萬元;五峰鄉市街景觀風貌形塑及街道管線整理改善計畫,核定三千九百萬餘元。三案都是中央補助八十二%,地方自籌十八%。

  • 新竹縣尖石鄉司馬庫斯部落聯外道路千瘡百孔,縣府和尖石鄉公所提案爭取前瞻基礎建設計畫,獲核定一億一千七百七十萬元。 (記者廖雪茹攝)

    新竹縣尖石鄉司馬庫斯部落聯外道路千瘡百孔,縣府和尖石鄉公所提案爭取前瞻基礎建設計畫,獲核定一億一千七百七十萬元。 (記者廖雪茹攝)

報導來源:自由時報【原文網址