Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈中部〉捷運綠線電聯車 主線測試順利 – 我是在地人

〈中部〉捷運綠線電聯車 主線測試順利

Booking.com

〔記者張菁雅/台中報導〕捷運綠線電聯車十二日起每天上主線進行實車介面測試,除測試列車性能、爬坡能力,並檢視軌道工程的配合度。交通局長王義川表示,目前測試相當成功,是為明年捷運綠線試運轉暖身,更象徵捷運工程邁向新里程碑。

來回六公里 經過爬坡及轉彎

電聯車由北屯機廠主維修廠出發,進入捷運綠線主線,至G5站後同軌折返,來回試行約六公里。交通局表示,測試區間經過爬坡段、松竹路轉北屯路與北屯路轉文心路兩處轉彎段,以及高架平面段,除可測試列車性能、爬坡能力外,並可檢視軌道工程的配合度,為後續電聯車上主線動態跑車奠定基礎。

王義川指出,目前捷運綠線已完成G0至G9站主線佈纜工程,電聯車所需的第三軌電力也在七月正式完成送電,在這次上主線測試前,交通局及施工單位也做好安全監測機制,已預先進行軌道淨空檢查,昨天電聯車上線前,再次派員巡視軌道,以確保電聯車於主線行駛時不會碰撞介面設施。

另外,捷運綠線工程進度已達七十一.三八%,而捷運綠線共有十八列電聯車,截至七月底,已有五台列車運抵北屯機廠,在日本原廠製造的七台列車也預定今年底完成組裝,運送來台。交通局表示,目前行控中心正在施工中,整體機電設施系統也全面進場施做,預計明年完成機電全系統整合測試後,明年底移交捷運公司進行試運轉,穩健朝一○九年通車目標邁進。

  • 台中捷運綠線電聯車上主線進行測試,除測試列車性能、爬坡能力,並檢視軌道工程的配合度。(台中市政府提供)

    台中捷運綠線電聯車上主線進行測試,除測試列車性能、爬坡能力,並檢視軌道工程的配合度。(台中市政府提供)

  • 台中捷運綠線電聯車進行主線測試。(台中市政府提供)

    台中捷運綠線電聯車進行主線測試。(台中市政府提供)

報導來源:自由時報【原文網址