Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈中部〉彰化高鐵聯絡道 拚年底全線通車 – 我是在地人

〈中部〉彰化高鐵聯絡道 拚年底全線通車

Booking.com

通往林厝交流道

〔記者顏宏駿/田中報導〕高鐵彰化站啟用後人氣始終低迷,民眾認為高鐵離人口最密集的員林市太遠所致,彰化縣府為解決問題,希望讓林厝交流道至高鐵站區的聯絡道早日通車,這條長達九公里的聯絡道目前只完成前半段,後半段縣府積極督促包商加緊趕工,希望拚年底全線通車。

田中、社頭地區近日瘋傳「高鐵聯絡道十月底就要通車」消息,讓當地民眾相當興奮,縣府工務局長林漢斌昨天證實,十月底通車的是二A標,該段從站區跨越社斗路到永靖與田尾鄉交界處,全長一.二公里,這段通車可讓田尾、永靖鄉、社頭鄉的民眾更快到達高鐵站,至於全線通車預定在今年底,但他們會加速趕工,希望在十一月底就能全線完工通車。

第二標全力趕工

高鐵彰化站區通往林厝交流道的聯絡道全長九公里三百七十六公尺,為了提早開通,在前縣長卓伯源主政時即同時開兩個標,第一標四.七公里已於去年底通車,第二標從永靖鄉到站區,因之前道路週邊地主還有意見,致拖慢時程,但縣府目前已一一排除,為加快完工時程,又分成二A和二B標。

林漢斌表示,二A標工程進度超前七.八%,為配合十一月十二日登場的「田中馬拉松」,縣府盡全力趕在十月底完工通車,目前路面都接近完工,部分路段開始畫線,待標誌、指示牌裝上,就可作通車前的履勘。

林漢斌指出,二B標工程會較慢的原因,係一間位於路面的土地公廟產權不明,挪移程序相當繁瑣,再加上稍早永靖鄉沿線多名地主對於施工有意見,因此拖延完工時程,目前這些問題均已排除,正在全面趕工中,預計十一月底可以完工,力拚年底全線完工通車。

報導來源:自由時報【原文網址