Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-sizes domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the ultimate-addons-for-gutenberg domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Notice: 呼叫 _load_textdomain_just_in_time 函式的方式不正確。Text Domain 為 astra 的語言套件載入過早觸發,這通常是由於外掛或佈景主題某些程式碼中的指示器過早執行所造成,而語言套件應該在 init 動作之後才載入。 請參閱〈WordPress 的偵錯功能〉以進一步了解相關資訊。 (這項訊息新增於 6.7.0 版) in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-includes/functions.php on line 6114

Deprecated: Creation of dynamic property nxs_wpAddnEngine::$k is deprecated in /var/www/vhosts/i-tw.com.tw/httpdocs/wp-content/plugins/nxs-snap-pro-upgrade/nxs-snap-pro-upgrade.php on line 11
〈南部〉南橫天龍吊橋修復 最快再等1年半 – 我是在地人

〈南部〉南橫天龍吊橋修復 最快再等1年半

Booking.com

〔記者王秀亭/台東報導〕台東縣天龍吊橋是南橫山區重要景點,從民國一○三年封橋迄今,尚無動工修復跡象,海端鄉公所表示,吊橋屬歷史建築,修復工法須審慎評估,已在規劃設計階段,若一切順利,完工開放還要再等一年半。

被列危橋 封橋3年半

位在霧鹿峽谷上的天龍吊橋興建於日治時期,全長一百一十公尺,是民眾上南橫必定造訪地之一,花東縱谷國家風景區管理處一○二年進行轄區觀光景點橋梁定結構鑑定後列為危橋,一○三年七月封橋,因屬歷史建築,經縱管處、海端鄉公所、台東縣政府協調後,由橋樑所屬及管理單位海端鄉公所著手規劃修復。

封橋三年半來,只有在颱風季節,南橫公路霧鹿以上道路坍方中斷,天龍吊橋才會暫時開放人員運送物資,不過車輛無法通行,天龍吊橋成了利稻村民唯一聯外的備用道路,卻因列為危橋,村民安危令人擔憂,不少遊客上南橫,就為了在吊橋上一覽霧鹿峽谷景色,不斷撲空,讓一旁的天龍飯店、霧鹿派出所頻頻解釋,仍被罵翻。

海端鄉公所財建課長薛清旺表示,天龍吊橋因列歷史建築,需在橋台樣貌不變的前提下,進行鋼索抽換、橋面面板更新,及強化橋墩基礎,調查研究及修復計畫送台東縣文化資產審議委員會審查,經過多次修正後通過,目前進入規畫設計階段。

縣文化處長鍾青柏表示,歷史建築修繕應盡量依原工法、原技術修復,但南側橋墩傾斜約十度,現在的岩盤條件相當不利,文資審議委員會審議過程中,文資委員針對工法、文化資產論述仍有許多建議,文化處持續積極協助,待規劃設計案通過,亦會協助向中央申請經費。

薛清旺指出,修復經費初估需一千兩百萬元,若計畫順利通過,文化部會與縱管處補助工程經費,儘快發包施工,最快明年中就能恢復天龍吊橋交通和觀光的功能。

  • 天龍吊橋興建於日治時期。(記者王秀亭攝)

    天龍吊橋興建於日治時期。(記者王秀亭攝)

報導來源:自由時報【原文網址